NextDC Halts Work on Projects Without Contracts After Data Center Issues in Australia
NextDC has stopped work on projects without contracts after issues at a data center in Melbourne.
The company said it would halt work on all projects without client contracts after a major setback at a facility in Melbourne, while two major rivals acquired a 9.9% stake in the company.
The delay in the expansion of the flagship data center M3 in Melbourne due to power supply delays and community resistance forced the company to lower its profit expectations last month, causing a 42% drop in its stock price.
NextDC CEO Craig Scroggie said the company’s priority was to win community support for the M3 project and that ’everything that doesn’t have a client contract and commitment is no longer a priority'.