Crete's Data Center Capacity Must Be Assessed Before Electricity Commitment
The Technical Chamber of Western Crete calls for a thorough assessment of the island's capacity before committing to data center development.
The Technical Chamber of Western Crete has emphasized the need for a thorough assessment of Crete’s capacity before committing to data center development. The chamber has highlighted the challenges of providing electricity, water, and land for data centers on the island. Crete has limited available electrical space, with a study by PwC estimating that the island can accommodate around 140 MW of new data centers by 2034, the smallest capacity among the regions studied. The chamber has also noted that the connections to the Peloponnese and Attica have a nominal capacity of around 1,400 MW, but the remaining capacity is much smaller during the peak summer months.